- Practical completion of the Rugby Club was achieved on 30 January 2020.

- The roof level structures of the Lacrosse building have been completed and the internal fittings on the ground floor are currently being completed. The Lacrosse building will be completed in late April 2020.

- The roof level structures of the Football and Cricket building is nearing completion. The Football and Cricket building will be completed in early June 2020.

- Final development approval for the Lacrosse field lighting has been achieved. Tenders have been called with the successful contractor to be engaged late February.

- Detailed design for the remainder of the civil works is being developed and tenders will be called in late February 2020.

- The contract for the LED scoreboards for each of the playing fields has been awarded with installed due in the coming months.

- Due to the upgrade of the new 3:3 basketball court and landscaping, the skate park will be out of action until mid-march 2020.