Project Update October 2019

9 months ago

Project Progress

  • Construction of the Rugby building is on schedule with completion forecast for January 2020. Milestones include pouring of the 1st floor slab and drop-down balcony. Construction of the roof has commenced.

  • Final designs for the Lacrosse, Football/Cricket Club buildings are completed and development approvals have been achieved.

  • Site possession for the demolition of the main grandstand and construction of the Lacrosse Club will occur in October. The two remaining clubrooms are forecast for completion approximately by end of June 2020.

  • Some car parking will be restricted for the construction period. Brighton Primary School has been consulted with.