Southern Site - Progress Update

7 November 2025

The Southern Site is nearing completion, with the crossing taking shape. The kerb ramps, pedestrian refuge and bus stop have been poured, with the footpath underway. The remaining civil works—road reinstatement and retaining wall —require final touches. The aim is to complete all civil works in the second week of October, weather permitting.

Aftercare will be in place, including delineation bollards and speed signage, until the new signage and line marking are installed, which will take place closer to the end of the project.

Southern Site - Pedestrian Refuge
Southern Site - Bus Stop