Works nearing completion

28 April 2026

Works are nearing completion at the Gross Pollutant Trap site. The GPT units have been successfully installed, and the seawall rock revetments have been reinstated.

There are two activities remaining: the maintenance access steps and the placement of duckbill valves on the pipe outlets. These activities will be carried out with a local path and /or road closure as required.

The Esplanade, Harrow Road and the coast park path will be reopened and swept of loose material.

We thank you for your patience during this project. We look forward to preventing a large amount of waste from entering the oceans.